Leading the design team and project team from concept through to RIBA Stage 4
Works out to tender Spring 2021 and due to complete Winter 2021
Liaising with various stakeholders throughout the project.
Coordinating the tender process through an appointed framework provider, Procure Partnerships Northwest
Three storey, six class room extension, Value £900k
Client’s requirements
DAY Project Management have lead the design team up to RIBA Stage 4 with the project out to tender March 2021. The three-storey side extension will provide the school additional teaching spaces to allow their continued growth.
The extension takes inspiration from the oxidised copper central core but has required a great deal of coordination and investigative works due to incoming services and attenuation tanks sited where the build is intended.
Contractor appointment is expected Spring 2021
Our Contribution
Liaised closely with all key stakeholders, project team, construction team
Proactively managing the design team through to tender stage
Tracking change during the project and ensuring correct sign off procedures to monitor budget.
Producing programmes to provide the school with a detailed delivery schedule
Key control mechanisms are put in place for this project such as Change Control Forms.